January 14 , 2005
- Storrs Downtown Parking Garage Presentation (Steve Maun/Leyland Alliance)
- Board of Trustee materials - Project Timelines for 21st Century UConn. (Lori/Linda)
- Arjona/Monteith Project (George/Fred)
Decisions: January 7, 2005 Meeting
1. There is a need to begin meetings at the appointed starting time. The group voted unanimously that until further notice, all academic year B&G meetings will take place from 9:00 a.m. to 11:30 a.m.
2. Space is needed for new personnel being hired in the Fire Inspector's Office. G. Kraus to identify potential cottage space.
3. The Greenhouse located at the Agronomy Farm has been condemned and is about to collapse. This structure is necessary programmatically for the Plant Science Department, and is also critical for providing swing space in the campus greenhouse plan. J. Greger to contact M. Musgrave for building kit options to replace this greenhouse. Broader discussion regarding the funding of the greenhouse plan occurred; IDC funds will be used over the next 5-year period to complement the $3 million provided through 21 st Century UConn to facilitate implementation of the greenhouse plan.
4. B&G Website. D. Carone will upload the website with added Guidelines and Flow Chart for public access by the end of January 2005.
5. Fire alarm system upgrades were discussed. Some will be implemented immediately. Others will require being a part of an overall campus system upgrade.
For Future Meetings:
- IT Plan - begin September; progress end date, mid-December/early January (Linda/Mike/Randy)
- Additional High Tech Classrooms schedule, training, size, mix, and baseline standard (Veronica's group) report due in November
- Master Plan Delivery Access (JJR to do map) site Rec II before we can do
- 21st Century UConn Equipment, Library Collections & Telecommunications: need to establish outcomes goals, revenue strategies and budget need start with equipment, report September, before next retreat
- Honors Program Complex estimated $5M, will site when donor identified (South Campus completion)
- Generic Lab Design teaching labs, to commence, need for Torrey (George/Ross/Janet)
- Written Report One-Card: Reconstitute one-card group (John) - TBA
- Composting Presentation Jan 28 (Rich)
- Common Clinic Building (Dale/Ross/Lori to come up with plan)
- Meeting with Provost's Clinic Building Working Group January (Dale/Ross/Lori)
- Campus Bicycle Plan survey and research results (Lisa Aultman-Hall and UConn ITE - Jan. 21)
- Stamford Parking Garage to be part of multi-year plan ® (George)
- Depot Campus Draft Plan (Janet)
- Parking Master Plan ® - working group being convened to rework
- Current Hall Dorm Plan ® report decisions from retreat (Dale)
- Work on Fairfield Way access with Public Safety (Karla/John/Dale)
- Torrey Design Review lab review (Ross/Janet)
- Ross, Ronnie, Cameron, Janet to come up with model for space discipline, needs to be like a separate research committee with included representation from B&G cf.: UCHC (Trutter, Carlson, Whetstone)
® Revisited from earlier meeting